Microgrids and Resliency Strategies
R. 19-09-009
June 17, 2020

D. 20-06-017 Microgrids Track 1 Final Decision

In support of SB 1339, Track 1 requires IOUs to expedite resiliency projects and enhance collaborations to help remove barriers to microgrid projects.

Requires IOUs to:

  • Expedite interconnection processes for microgrid and resiliency projects;
  • Modify NEM requirements;
  • Remove battery storage limits;
  • Collaborate with local and tribal governments (including CCAs); and
  • Submit multiple advice letters.

SDG&E Local Area Distribution Controller (LADC) proposal conditionally approved.

SDG&E proposed EV charging structure at Cameron Corners microgrid is denied due to lack of information in multiple required categories. SDG&E may resubmit.

Update Links
D. 20-06-017
SEE PROCEEDING