BACK
Microgrids and Resliency Strategies
R. 19-09-009
March 10, 2021
Reply Comments on Track 3 Scoping Memo
The debate continues over which types of entities/microgrids should be exempt from standby charges.
SDG&E:
- Commission should dismiss any further discussion of waivers- parties fail to show equity of exemption of standby charges.
- Resiliency & Microgrids WG should examine the value of resiliency.
- False for parties to assert POLR obligations are negated by PSPS.
SEIA/Vote Solar:
- Question of standby charges should focus on customers who are currently subject to standby charges.
- Commission should articulate cost causation for standby charges as distinct from departing load or other types of charges.
- Consider payment of standby charge to microgrid customers who have resources that can be made available to remove load from the grid in response to IOU signal and thereby reduce or avoid rotating outages.
Update Links