The investor-owned utilities ("IOUs") hosted a public workshop, then filed a joint Tier 2 advice letters ("ALs") in compliance with Ordering Paragraph ("OP") 8 or Resolution E-5167 and OP 4 of Resolution E-5168. The AL proposes an average project timeline and actions to improve project timelines associated with the EV Infrastructure Rules.

The AL was filed for:

  • San Diego Gas & Electric: AL 4011-E
  • Bear Valley Electric Service: AL 444-E
  • Liberty Utilities: AL 192-E
  • Pacific Gas & Electric: AL 6607-E
  • PacificCorp: AL 685-E
  • Southern California Edison: AL 4803-E

The AL proposes the following timeline and actions:

  1. The IOUs propose an average numerical target of 160 business days.
  2. The average numerical target should only apply to steps within the IOU's direct control for EV Infrastructure Rules work.
  3. The average numerical timeline should not apply to steps that are not directly within the IOUs' control.
  4. The IOUs are committed to making ongoing improvements to the energization timeline for customers.
  5. The IOUs can contribute to improving timing processes outside of their control.
  6. The IOUs find some of the feedback collected from stakeholders during and after the energization public workshop infeasible.
Update Links
SDG&E AL 4011-E
SEE PROCEEDING
RELATED UPDATES

Client Resources

Land Use

Regulatory

Litigation

About

845 15th Street, Suite 103
San Diego, CA 92101
858-224-3068