BACK
Net Energy Metering ("NEM")
R. 20-08-020
June 2, 2022
ALJ Ruling Grants Public Advocates Office's Request to Establish Page Limits and Extend the Deadline for Party Comments
In response Public Advocates Request relating to the May 9, 2022 ALJ Ruling Setting Aside Submission of the Record to Take Comment on a Limited Basis, the Commission grants the request to limit opening comments to 25 pages and reply comments to 10 pages as well as extend the time for reply comments to July 1, 2022.
Update Links
ALJ Ruling (6/2/2022)RELATED UPDATES
R. 20-08-020
ALJ Issues Ruling Seeking Additional Input on NEM 3.0 Proposed Decision
SEE UPDATE